WHAT:
Asphalt Grind/Inlay
WHEN:
September 23
TIMING:
5am-7pm **REVISED TIME**
IMPACT:
REVISING TIMING: Work will begin earlier than previously scheduled (5AM) to maximize the efficiency of operations and to minimize the duration, thereby reducing the impact. Please be advised residents in the area may hear construction noises starting at (5AM).
For the duration of the project, there will be alternating flagging north and south. The definition of “restricted access” is a manned barricade to dissuade drivers for using, but allowances will be made for residents, busses and emergency vehicles.
WHERE:
32nd Street between J Street and W Street
WHY:
The asphalt grind/inlay is a key part of the City of Washougal’s preventative maintenance program to maximize the service life of public roads.
HOW:
Grind/inlay involves grinding areas of pavement failure to a depth of 2-3” and pouring new asphalt in place. The new asphalt must be compacted and allowed to cool prior to letting traffic on it.
ADDITIONAL INFORMATION:
On the day of the grind/inlay we will need your help to expedite the work:
- Limit pedestrian activity near the work area. There will be a lot of machinery in the area and we want everyone to be safe.
- Park your vehicle on another street if possible
Our goal to minimize any inconvenience this work might cause.